Neri told the court that an accepted email quotation recorded an agreement for six shelves at a price of €3,000, with a €1,800 advance and completion by 12 September. She said she also had a bank transfer record for the advance. Although she requested softer front edges, she understood this to be a small adjustment rather than a change to the deadline.
According to Neri, four shelves were mounted on 16 September, while two boards were unusable because brackets were missing. She acknowledged using some of the mounted shelves and did not maintain that everything delivered was worthless. She said she refused Bellandi's proposed return on 18 September because the shop was already operating and she had lost confidence after the missed date.
Bellandi submitted that the edge change required him to rework finished pieces and that Neri had agreed to his coming on 16 September. He accepted that he had not clearly agreed a new final completion date and that the work was not fully finished.
Bellandi said four shelves were usable and the remaining two needed only a short visit to fit brackets. He argued that the €1,800 advance fairly reflected the work Neri retained, while acknowledging that the quotation did not assign a separate value to each shelf. He sought dismissal of the repayment claim or a reduction limited to genuinely unfinished work, with no payment for temporary stands.